John Lewis Bluewater
Description: Sales Floor, Café area lighting
To remove all existing till points and PC stations on all floors
Reconfigure existing shop fit across various departments to allow install of new shop fit and department refreshes
Install new POS equipment and manage shop fitters and project plan
No disruption to trading of store
Project Brief:
Remove existing POS systems and till point shop fit
Remove all existing power and data
Remove and reconfigure shop fit
Remove and reconfigure selective perimeter displays
Install new power and data
Install new pos and shop fit
Manage the install of new raised flooring and "bolted on" projects around the store whilst managing above project
Project Duration: 9 Weeks
Guardian Project Role: Electrical and Data installers, Lead Contractors, Project Managers
Project Value: Approx £450,000.00